With
the DD 692 SUMNER class continuing to be overloaded with anti-aircraft
capabilities to protect the carrier forces, the resulting effect was a lack of
speed and required range. By 1943, Adm. King accepted the BuShips recommendation
that the SUMNER hull be lengthened by 14 feet so that an additional 160 tons of
fuel could be carried resulting in an increase of range over the basic SUMNER by
30 percent. The first ship to receive this new hull, was
the GEARING (DD-710) and it became the lead ship of the 2,200 ton GEARING class
destroyers. Of the 98 commissioned GEARING class
destroyers, 47 retained their DD classification prior to FRAM with three being
disqualified due to having been modified for improved steam machinery testing (TIMMERMAN),
advances in missile technologies (GYATT) and testing of an advanced propulsion
system (WITEK). Of the remaining 44, ALL GEARINGS received the FRAM MK I
reconstruction.
With the 14 foot extension provided in the middle of the
ship, the added space proved vital in relocating some machinery for better
balance whereas the Sumners were noted for being "Bow heavy". Other
than the 14 foot extension, the SUMNERs and GEARING class destroyers were
visually identical.
HOW FRAM EVOLVED For the GEARING class:
By FY 1959, there remained 44 original GEARING class destroyers
that had not been converted into either dedicated submarine warfare destroyers
(DDE), hunter-killer destroyers (DDK), radar picket destroyers (DDR) or for
specialized research. Further,
several GEARINGS were simply not completed with their various parts going to
other GEARINGs damaged in the course of operations (see "notes"
below). The longer length GEARING class made excellent candidates for the FRAM
program and while only 49 of ALL
variants of GEARING class destroyers were scheduled for
FRAM, that number eventually grew to include 80 vessels of the 98 commissioned.
Of the remaining 18, 15 vessels received the MK 2 modernization.
The first GEARING to receive FRAM was the
PERRY (seen left) whose conversion commenced on 1 May 1959 and was
completed on 1 April 1960 at the Boston Naval Shipyard. At a cost of $
7,700,000, the FRAM MK 1 reconstruction level PERRY received set the level for
all GEARINGS, except the WITEK. This reconstruction included the installation of
ASROC aft of the first stack, the DASH hangar and flight deck, the new SQS-23
sonar system and dome which had a detection range of 40,000 yards as well as
either the SPS-29, -37 or -40 air-search radar which was needed to track the
DASH helicopter in flight. Also included was the installation of two MK-32
triple torpedo launchers as well as a new superstructure with the main machinery
either being replaced or overhauled. From the propellers to the shafts to the
distilling plant to fuel systems, all machinery systems were either overhauled
or replaced while maintaining below decks arrangement. The top deck however,
with the installation of the DASH flight deck and hangar along with the ASROC
launcher installed required a complete rearrangement.
The FRAM MK 1
reconstruction was somewhat different for the top deck
arrangement of the GEARINGS. There were 2 variants of the FRAM MK-1 for the
GEARINGS:
| GROUP A Ships: Removal of aft Twin 5 inch/38 caliber
Gun mount (mount 53). GROUP A ships also received two MK10/11 Hedgehogs
fitted on each side of the bridge at the O-1 level and had their MK-32
triple torpedo launchers aft of the second stack.
|
| GROUP B Ships: They kept their more forward 5 inch
mount (mount 51), lost the second mount (Mount 52) behind it and kept their
aft 5 inch mount (mount 53). In place of mount 52, a practice 5 inch
reloading machine was installed with the MK-32 triple torpedo launchers aft
of the loader. Group B ships also received greater ASROC and torpedo storage
areas next to the port side of the DASH hangar.
|
Herein is the listing of ALL non-converted 44 GEARING Class destroyers
(DD) existing
as of 1960; those ships that received either the GROUP A or B variation of FRAM
MK I are noted as such. Total cost to FRAM this class: $ 338,500,000.
GEARING CLASS DESTROYERS
(all received FRAM Mk I)
|
Name of Ship
|
Hull No.
|
Group Variant
|
Builder
|
Launched
|
Stricken Date
|
AGERHOLM
|
826
|
A
|
Bath Iron Works, Bath ME
|
30 Mar 1946
|
01 Dec. 1978
|
ARNOLD J. ISBEL
|
869
|
B
|
Bethlehem Steel, Staten Island, New York
|
06 Aug. 1945
|
01 Feb. 1974
|
BAUSSELL
|
845
|
A
|
Bath Iron Works, Bath ME
|
19 Nov. 1945
|
30 May 1978
|
BRINKLEY BASS
|
887
|
B
|
Consolidated Steel, Orange TX
|
26 May 1945
|
03 Dec. 1973
|
BROWNSON
|
868
|
A
|
Bethlehem Steel, Staten Island, New York
|
07 July 1945
|
30 Sept. 1976
|
CHARLES H. ROAN
|
853
|
B
|
Bethlehem Steel, Quincy
|
15 Mar. 1946
|
21 Sept. 1973
|
CHARLES R. WARE
|
865
|
B
|
Bethlehem Steel, Staten Island, New York
|
12 Apr. 1945
|
30 Nov. 1974
|
|
866
|
B
|
Bethlehem Steel, Staten Island, New York
|
10 May 1945
|
01 Oct. 1982
|
EVERSOLE
|
789
|
B
|
Todd Pacific Shipyards, Seattle
|
08 Jan. 1946
|
21 Sept. 1973
|
FLOYD B. PARKS
|
884
|
B
|
Consolidated Steel, Orange TX
|
31 Mar. 1945
|
02 July 1983
|
FORREST ROYAL
|
872
|
B
|
Bethlehem Steel, Staten Island, New York
|
17 Jan. 1946
|
01 Feb. 1973
|
GEARING
|
710
|
B
|
Federal Ship Building & D.D. Co. Newark, NJ
|
05 Mar. 1944
|
01 July 1973
|
GEORGE K. MACKENZIE
|
836
|
B
|
Bath Iron Works, Bath ME
|
13 May 1945
|
01 Oct. 1976
|
GLENNON
|
840
|
B
|
Bath Iron Works, Bath ME
|
14 July 1945
|
01 Oct. 1976
|
GURKE
|
783
|
B
|
Todd Pacific Shipyards, Seattle
|
15 Feb. 1945
|
30 Jan. 1976
|
HAMNER
|
718
|
B
|
Federal Ship Building & D.D. Co. Newark, NJ
|
24 Nov. 1945
|
01 Oct. 1979
|
HAROLD J. ELLISON
|
864
|
B
|
Bethlehem Steel, Staten Island, New York
|
14 Mar. 1945
|
01 Oct. 1983
|
HENDERSON
|
785
|
B
|
Todd Pacific Shipyards, Seattle
|
28 May 1945
|
30 Sept. 1980
|
HOLLISTER
|
788
|
B
|
Todd Pacific Shipyards, Seattle
|
09 Oct. 1945
|
31 Aug. 1979
|
JAMES E. KYES
|
787
|
B
|
Todd Pacific Shipyards, Seattle
|
04 Aug. 1945
|
31 Mar. 1973
|
JOHN R. CRAIG
|
885
|
B
|
Consolidated Steel, Orange TX
|
14 Apr. 1945
|
27 July 1979
|
JOHNSTON
|
821
|
B
|
Consolidated Steel, Orange TX
|
19 Oct. 1945
|
27 Feb. 1981
|
|
850
|
B
|
Bethlehem Steel, Quincy
Preserved as memorial; berthed at Fall River, Mass
|
26 July 1945
|
01 July 1973
|
LEONARD F. MASON
|
852
|
B
|
Bethlehem Steel, Quincy
|
04 Jan. 1946
|
02 Nov. 1976
|
MEREDITH
|
890
|
A
|
Consolidated Steel, Orange TX
|
28 June 1945
|
07 Dec. 1979
|
NOA
|
841
|
A
|
Bath Iron Works, Bath ME
|
30 July 1945
|
02 June 1975
|
|
886
|
B
|
Consolidated Steel, Orange TX
Preserved as memorial; berthed at Orange,
Texas
|
12 May 1945
|
06 Aug. 1987
|
OZBOURN
|
846
|
B
|
Bath Iron Works, Bath ME
|
22 Dec. 1945
|
01 June 1975
|
PERRY
|
844
|
A
|
Bath Iron Works, Bath ME
|
25 Nov. 1945
|
01 July 1973
|
POWER
|
839
|
B
|
Bath Iron Works, Bath ME
|
30 June 1945
|
01 Oct. 1977
|
RICHARD B. ANDERSON
|
786
|
A
|
Todd Pacific Shipyards, Seattle
|
07 July 1945
|
30 Jan. 1976
|
RICHARD E. KRAUS
|
849
|
B
|
Bath Iron Works, Bath ME
|
02 Mar. 1946
|
01 July 1976
|
ROBERT H. McCARD
|
822
|
B
|
Consolidated Steel, Orange, TX
|
09 Nov. 1945
|
06 Aug. 1987
|
ROWAN
|
782
|
B
|
Todd Pacific Shipyards, Seattle
|
29 Dec. 1944
|
30 Jan. 1976
|
RUPERTUS
|
851
|
B
|
Bethlehem Steel, Quincy
|
21 Sept. 1945
|
10 July 1973
|
SAMUEL B. ROBERTS
|
823
|
B
|
Consolidated Steel, Orange, TX
|
30 Nov. 1945
|
02 Nov. 1970
|
SARSFIELD
|
837
|
B
|
Bath Iron Works, Bath ME
|
27 May 1945
|
01 Oct. 1977
|
SHELTON
|
790
|
A
|
Todd Pacific Shipyards, Seattle
|
08 Mar. 1946
|
31 Mar. 1973
|
STRIBLING
|
867
|
B
|
Bethlehem Steel, Staten Island, New York
|
08 June 1945
|
01 July 1976
|
THEODORE E. CHANDLER
|
717
|
B
|
Federal Ship Building & D.D. Co. Newark, NJ
|
20 Oct. 1945
|
01 Apr. 1975
|
VOGELGESANG
|
862
|
B
|
Bethlehem Steel, Staten Island, New York
|
15 Jan. 1945
|
24 Feb. 1982
|
WARRINGTON
|
843
|
B
|
Bath Iron Works, Bath ME
|
27 Sept. 1945
|
01 Oct. 1972
|
WILLIAM C. LAWE
|
763
|
B
|
Bethlehem Steel, San Francisco
|
21 May 1945
|
01 Oct. 1983
|
WILTSIE
|
716
|
B
|
Federal Ship Building & D.D. Co. Newark, NJ
|
31 Aug. 1945
|
30 Jan. 1976
|
*NOTES concerning GEARING class
destroyers:
| LANDSDALE (DD- 766): Although laid down by
Bethlehem Steel of San Francisco on April 2, 1944 with launching by December
20, 1946, construction was halted with the uncompleted LANDSDALE being
stored at Suisun Bay, Ca. The uncompleted LANDSDALE eventually lost a 60-ton
portion of its bow to repair the Floyd B. Parks (DD-884) which was damaged
on 11 March 1956 when she collided with heavy cruiser, USS Columbus (CA 74).
Landsdale was never completed or commissioned and subsequently stricken on 9 June 1956.
|
| SEYMOUR O. OWENS (DD-767): The uncompleted
OWENS lost its 165-ton bow to repair the Ernest G. Small (DDR-838) which was
damaged when that ship struck a mine off Sonjin, Korea on 7 Oct. 1951.
Owens was never completed or commissioned and subsequently stricken on 9 June 1956.
|
| SEAMAN (DD-791): Although
laid down by Todd Shipyards of Seattle on July 10, 1945 and launched May 29,
1946, her construction was stopped with her incomplete hulk stored until she
was stricken 1 March 1961 and subsequently sold and broken up for scrap.
|
| TIMMERMAN (EDD-828): Although
laid down by Bath Iron works, Bath, ME on October 1, 1945 as a GEARING class
destroyer, work on TIMMERMAN
(seen right) ceased three months later.
She was reclassified as an experimental destroyer (EDD 828) to test new and more
efficient steam-propulsion. Designed to occupy the same
space in standard GEARING engine spaces, the TIMMERMAN's machinery was designed to
generate 100,000 SHP vs. the GEARING's 60,000 SHP. This was done by having
on the port side, a General Electric Turbine 2,000 PSI/1,050 degrees F
operating steam-propulsion plant and on the starboard side, a Westinghouse
turbine 875 PSI/1,050 degrees F steam-propulsion plant. With construction
work resuming by May 1946 and commissioning
by September 26, 1952, the TIMMERMAN tested and evaluated its' new steam
machinery technologies extensively, yet its service life was short. Due to
extensive modifications to the ship to accomplish its steam testing, it was
deemed not worth receiving FRAM. Reclassified as AG 152 in 1954, she was
decommissioned on 27 July 1956 and stricken 4 April 1958 and sold for scrap.
|
| WITEK (EDD-848): Although
laid down by Bath Iron works, Bath, ME on 16 July 1945 as a GEARING class
destroyer and launched 2 February 1946 with commissioning 25 April 1946,
WITEK served as a Experimental Destroyer for most of her career. WITEK
received a
"pump jet" type propulsion system reclassifying it as EDD 848 in
1959. While quieter, It never received FRAM due to its' propulsion system
and cost to convert to standard machinery. WITEK was stricken 17 September
1968 and sunk as a target on 4 June 1969, off the coast of Virginia.
|
| GEARING Class Destroyers not commissioned and SCRAPPED
before complete:
|
| CANCELLATIONS - The following hulls were
cancelled before being laid down: DD 809-816, 854-856, and 891-926.
|
GEARING CLASS DESTROYER POST-FRAM
SPECIFICATIONS
|
Displacement:
|
2,425 tons standard (3,479
tons full load)
|
Dimensions:
|
390 1/2 x 40' 10" beam x 18'6" maximum draft
|
SONAR:
|
SQS-23 Sonar System
|
Air Search Radar:
|
SPS-29, -37 or -40
|
Height Finding Radar
|
SPS-8 or -30
|
Surface Search Radar
|
SPS-10
|
Guns:
|
2 qty, TWIN 5 inch/38 caliber MK 12 mod 1 guns installed on MK 38 gun
mount
|
Weapons:
|
ASROC and 2 qty, DASH Helicopters, 6
homing torpedo tubes (2 MK 32 Triple Torpedo mounts). TWO Mark-10,
7.2" HEDGEHOG Projector ( "ahead-thrown-missiles" launches
24 - 7.2 inch missiles with contact fuses) location dependent on Group
model of FRAM I.
|
Machinery:
|
2 Westinghouse turbines coupled to 2 DeLaval locked-train double
reduction gears. 2 shafts, 350 RPM, SHP: 60,000 = 34.5 knots
|
Boilers:
|
FOUR Babcock & Wilcox working pressure 565 PSI at 850 degrees F
|
Oil Fuel:
|
4,647 barrels NSFO and 167 barrels of Diesel Oil = 650 tons
|
Radius:
|
At 2,425 tons standard maximum speed is
34.5 knots with endurance of 6,500 miles at 15 knots
At 3,479 tons full load maximum
speed is 31.3 knots with endurance of 5,370 miles at
15 knots
|
Complement:
|
Allowance: 355 (20 officers, 325 enlisted men)
|
|
BEFORE and AFTER FRAM
|
|
|
|
BEFORE: At left,
as seen before her FRAM MK I reconstruction, the USS GURKE (DD-783) showing
her distinctive triple, twin barrel 5 inch/38 caliber mounts as well as
the 2x 3"/50 cal machine guns, 3x40mm and 10x20 mm anti-aircraft
batteries as well as the MK 15 1x5 tube torpedo launcher amidship. Along
with its MK6 K-gun depth charge projector as well as two MK9 depth charge
racks, this was the post-World War II configuration for the GEARING class
destroyer. AFTER it received its FRAM reconstruction in May 1964,
the GURKE lost all of the above, save for two 5 inch/38 caliber mounts.
|
|
|
AFTER:
At right, the USS GEORGE K. MAC KENZIE (DD
836) is show after her FRAM MK I reconstruction she received at the New
York Naval shipyard in December 1963. Note the MK-112 ASROC launcher
between the stacks as well as the DASH Hangar aft of the no. 2 stack. Both
MAC KENZIE and GURKE were "Group B" variants of the FRAM MK I
program in that they kept their more forward 5 inch
mount (mount 51), lost the second mount behind it (Mount 52) and kept their
aft 5 inch mount (mount 53). In place of mount 52, a practice 5 inch
reloading machine was installed with the MK-32 triple torpedo launchers aft
of the loader. Group B ships also received greater ASROC and torpedo storage
areas next to the port side of the DASH hangar.
|
|
|
The USS MEREDITH (DD-890)
in her post FRAM outfit showing the aft Hangar and landing deck for her
newly installed DASH system as well as new superstructure. MEREDITH was a
"GROUP A" variant of the FRAM MK I reconstruction in that they
had the aft Twin 5 inch/38 caliber
Gun mount (mount 53) removed. GROUP A ships also received two MK 10/11 Hedgehogs
fitted on each side of the bridge at the O-1 level and had their MK-32
triple torpedo launchers aft of the second stack.
Laid down by Consolidated
Steel in Orange Texas on January 27, 1945, launched on June 28, 1945,
Commissioning on December 31, 1945, completed FRAM at the Philadelphia
Navy Yard in June 1961, she served for 34 years until being stricken on
December 7, 1979. She was subsequently sold to Turkey on 20 March 1980 and
renamed Savastepe. She was eventually broken up for scrap in March
1995.
|
|